3
NEW FERC issuances since 2016-10-07 10:15:01.480844

Case Title/
Accession Number
Docket NumberDescriptionFERC
AMERICAN TRANSMISSION COMPANY, L.L.C.
20161007-3027

EC16-137
Order Authorizing Acquisition of Facilities re American Transmission Company LLC under EC16-137. PDF
Word
PDF
Word
BUCKSPORT MILL, L.L.C.
20161007-3021

EC16-163
Order Authorizing Disposition of Jurisdictional Facilities re Bucksport Mill LLC under EC16-163. PDF
Word
PDF
Word
GE ALBANY GLOBAL HOLDINGS BV
20161007-3020

EC16-144
Order on Prospective Authorization for the Acquisition and Disposition of Jurisdictional Facilities re GE Albany Global Holdings BV et al under EC16-144. Word
PDF
Word
PDF
GREAT PLAINS ENERGY, INC.
20161007-3019

EC16-146
Deficiency Letter for the Joint Application for Authorization of Disposition of Jurisdictional Assets and Merger Under Sections 203(a)(1) and 203(a)(2) of the Federal Power Act. Word
PDF
Word
PDF
MIDCONTINENT INDEPENDENT SYSTEM OPERATOR, INC.
20161007-3008

ER16-696
Order Denying Rehearing re Midcontinent Independent System Operator, Inc. under ER16-696. Word
PDF
Word
PDF
NEW YORK STATE ELECTRIC & GAS CORPORATION
20161007-3025

ER16-2571
Letter order accepting New York State Electric & Gas Corporation's 9/9/16 filing of an Executed Cost Reimbursement Agreement with Pennsylvania Electric Company under ER16-2571. PDF
Word
PDF
Word
PJM INTERCONNECTION, L.L.C.
20161007-3013

ER16-2494
Letter order accepting PJM Interconnection, LLC's 8/26/16 as supplemented 9/13/16 filing for an executed Wholesale Market Participation Agreement with Solar Access Development Group, LLC et al under ER16-2494. PDF
Word
PDF
Word
PJM INTERCONNECTION, L.L.C.
20161007-3024

ER16-2518
Letter order accepting PJM Interconnection, L.L.C.'s 8/31/16 filing of the Support Interconnection Request and Feasibility Study Process under ER16-2518. Word
PDF
Word
PDF
PJM INTERCONNECTION, L.L.C.
20161007-3026

ER16-2573
Letter order accepting PJM Interconnection, L.L.C.'s 9/9/16 filing of an executed Interconnection Service Agreement and Notice of Cancellation under ER16-2573. Word
PDF
Word
PDF
SOUTH CAROLINA ELECTRIC & GAS COMPANY
20161007-3022

ES16-51
Order Authorizing Issuances of Securities re South Carolina Electric & Gas Company et al under ES16-51. Word
PDF
Word
PDF
Case Title/
Accession Number
Docket NumberDescriptionFERC
AMERICAN MIDSTREAM (MIDLA), L.L.C.
20161007-3009

CP15-523
Letter order granting American Midstream, LLC's 10/6/2016 request to use an additional access road for the Natchez Pipeline Project under CP15-523. Word
PDF
Word
PDF
CAMERON LNG, L.L.C.
20161007-3014

CP13-25
Letter order approving Cameron LNG, LLC's 10/29/15 request, as supplemented on 6/10/16 notice to proceed with construction of liquefaction facilities under CP13-25. PDF
Word
PDF
Word
COLUMBIA GAS TRANSMISSION, L.L.C.
20161007-3010

CP13-8
Letter order granting Columbia Pipeline Group's 9/23/2016 request to place into service Phase IIC of the Line MB Expansion Project under CP13-8. Word
PDF
Word
PDF
FLORIDA SOUTHEAST CONNECTION, L.L.C.
20161007-4004

CP14-554
Environmental Inspection Report for Florida Southeast Connection, L.L.C.'s Florida Southeast Connection Project, conducted on September 20, 2016 under CP14-554. PDF
PDF
PDF
PDF
FLORIDA SOUTHEAST CONNECTION, L.L.C.
20161007-4005

CP14-554
Environmental Inspection Report forFlorida Southeast Connection, L.L.C.'s Florida Southeast Connection Project, conducted on August 15, 2016 under CP14-554. PDF
PDF
PDF
PDF
MILLENNIUM PIPELINE COMPANY, L.L.C.
20161007-3007

CP16-486
Letter requesting Millennium Pipeline Company, LLC to provide a response within 20 days re the Environmental Data Request for Resource Report 1-12 to assist in the analysis of the certificate application under CP16-486. PDF
Word
PDF
Word
TRANSCONTINENTAL GAS PIPE LINE COMPANY, L.L.C.
20161007-3023

CP15-117
Letter order granting Transcontinental Gas Pipeline Company, LLC's 9/20/16 request re for Notice to Proceed with construction of certain components of the Dalton Expansion Project under CP15-117. PDF
Word
PDF
Word
Case Title/
Accession Number
Docket NumberDescriptionFERC
ADF, INC.
20161007-5081

P-620
Letter to the City of Chignik Alaska providing follow-up comments to the 2016 FERC Dam Safety Inspection of the Chignik Project under P-620. PDF
PDF
PDF
PDF
ALASKA ELECTRIC LIGHT AND POWER COMPANY
20161007-5112

P-2307
Letter to Alaska Electric Light and Power Company regarding the Diversion Plug Sonar Inspection for the Salmon Creek Project under P-2307. PDF
PDF
PDF
PDF
ALASKA ENERGY AUTHORITY
20161007-5118

P-2742
Letter to Copper Valley Electric Association regarding the 2017 Emergency Action Plan (EAP) Exercise for the Solomon Gulch Project under P-2742. PDF
PDF
PDF
PDF
ALCOA POWER GENERATING, INC.
20161007-3029

P-2169
Order Modifying and Approving Revised Historic Properties Management Plan re Brookfield Smoky Mountain Hydropower, LLC under P-2169 et al. PDF
Word
PDF
Word
ATLANTA POWER COMPANY
20161007-5078

P-11541
Letter to Mr. Israel Ray providing follow-up comment to the 2016 FERC Dam Safety Inspection of the Atlanta Power Station Hydro Project under P-11541. PDF
PDF
PDF
PDF
AVISTA CORPORATION
20161007-5103

P-2058
Letter to Avista Corporation providing comments on the As-Built Drawings for the Cabinet Gorge Development of the Clark Fork Project under P-2058. PDF
PDF
PDF
PDF
BMB ENTERPRISES, INC.
20161007-3030

P-6764
Order Approving Documentation of Project Financing re BMB Enterprises, Inc. under P-6764. PDF
Word
PDF
Word
CITY OF ASHLAND, OREGON
20161007-5062

P-1107
Letter to the City of Ashland Oregon accepting the Plan and Schedule for addressing 2016 Dam Safety Inspection Follow-Up Items for the Reeder Gulch Project under P-1107. PDF
PDF
PDF
PDF
CITY OF ASHLAND, OREGON
20161007-5060

P-1107
Letter to the City of Ashland Oregon accepting the Revised Plan and Schedule Regarding the Seventh Part 12 Report for Hosler Dam Development of the Reeder Gulch Project under P-1107. PDF
PDF
PDF
PDF
CITY OF ASHLAND, OREGON
20161007-5061

P-1107
Letter to the City of Ashland Oregon providing comment on the 2015 Dam Safety Surveillance and Monitoring Report (DSSMR) for the Reeder Gulch Project under P-1107. PDF
PDF
PDF
PDF
CITY OF IDAHO FALLS, IDAHO
20161007-5119

P-2842
Letter to Idaho Falls power granting the 2017 Emergency Action Plan (EAP) Exemption for the Idaho Falls Project under P-2842. PDF
PDF
PDF
PDF
CITY OF IDAHO FALLS, IDAHO
20161007-5124

P-2952
Letter to Idaho Falls Power accepting the Plan and Schedule for addressing the comments on the Supplemental PFMA for the Gem Sate Project under P-2952. PDF
PDF
PDF
PDF
CITY OF PORTLAND, OREGON
20161007-5070

P-2821
Letter to the City of Portland Oregon regarding the FY16 Dam Safety Inspection Follow-Up Response Plan and Schedule, Portland Hydroelectric Project under P-2821. PDF
PDF
PDF
PDF
CITY OF PORTLAND, OREGON
20161007-5071

P-2821
Letter to the City of Portland Oregon regarding the FY16 Dam Safety Inspection Follow-Up Response Plan and Schedule, Portland Hydroelectric Project under P-2821. PDF
PDF
PDF
PDF
CITY OF SAN LUIS OBISPO, CALIFORNIA
20161007-3031

P-5218
Letter requesting City of San Luis Obispore to file a detailed plan and schedule for completing all work within 30 days re the Non-operating status for the San Luis Obispo Hydroelectric Project under P-5218. PDF
PDF
PDF
PDF
CITY OF SEATTLE, WASHINGTON
20161007-5125

P-2959
Letter to Seattle City Light providing follow-up comments to the 2016 FERC Dam Safety Inspection of the South Fork Tolt River Project under P-2959. PDF
PDF
PDF
PDF
CITY OF SPOKANE, WASHINGTON
20161007-5126

P-3074
Letter to the City of Spokane Washington providing comment on the Spillway Rehabilitation Phase II July 2016 Construction Report for the Upriver Project under P-3074. PDF
PDF
PDF
PDF
ERIE BOULEVARD HYDROPOWER, L.P.
20161007-3018

P-11408
Letter informing Erie Boulevard Hydropower, LP that the late filing of the notice regarding cancellation of whitewater releases will not be considered a violation of the license for the Salmon River Project under P-11408. PDF
PDF
PDF
PDF
GEORGIA POWER COMPANY
20161007-3016

P-1218
Order Granting Temporary Variance of Article 401 re Georgia Power Company under P-1218. PDF
Word
PDF
Word
GEORGIA POWER COMPANY
20161007-3011

P-1951
Letter informing Georgia Power Company that the oil release that occurred on 7/25/2016 will not be considered a violation of Ordering Paragraph (E) or Article 19 of the L-1 form re the Sinclair Hydroelectric Project under P-1951. PDF
PDF
PDF
PDF
GRANITE COUNTY, MONTANA
20161007-5135

P-12107
Letter to Granite County providing comments on the GIS Inundation Mapping for the Flint Creek Hydroelectric Project under P-12107. PDF
PDF
PDF
PDF
HORSESHOE BEND HYDROELECTRIC COMPANY
20161007-5128

P-5376
Letter to Horseshoe Bend Hydroelectric Co., acknowledging the 2016 EAP Revision No. 2 for the Horseshoe Bend Hydroelectric Project under P-5376. PDF
PDF
PDF
PDF
IDAHO POWER COMPANY
20161007-5084

P-1971
Letter to Idaho Power Company accepting the Revised Dam Breach Analysis and Inundation Mapping for the Hells Canyon Development of the Hells Canyon Project under P-1971. PDF
PDF
PDF
PDF
IDAHO POWER COMPANY
20161007-5085

P-1975
Letter to Idaho Power Company providing follow-up comments to the 2016 FERC Dam Safety Inspection of the Bliss Project under P-1975. PDF
PDF
PDF
PDF
IDAHO POWER COMPANY
20161007-5122

P-2899
Letter to Idaho Power Company providing follow-up comments to the 2016 FERC Dam Safety Inspection of the Milner Project under P-2899. PDF
PDF
LOVELAND, CITY OF
20161007-3028

P-2829
Order Modifying and Approving Request to Amend License for Powerhouse Removal re City of Loveland, Colorado under P-2829. PDF
Word
PDF
Word
MONTANA DEPARTMENT OF NATURAL RESOURCES
20161007-5120

P-2853
Letter to Montana Department of Natural Resources and Conservation regarding the Plan and Schedule to address the 2015 Dam Safety Surveillance and Monitoring Report Comments for he Broadwater Project under P-2853. PDF
PDF
PDF
PDF
PACIFICORP
20161007-5104

P-2082
Letter to PacifiCorp regarding the 2014 Part 12D Independent Consultants Report Supplement for the J.C. Boyle Development of the Klamath River Project under P-2082. PDF
PDF
PDF
PDF
PACIFICORP
20161007-5116

P-2381
Letter to PacifiCorp Energy providing comments on the 2015 Dam Safety Surveillance and Monitoring Report for the Ashton Hydroelectric Project under P-2381. PDF
PDF
PDF
PDF
PACIFICORP
20161007-5117

P-2381
Letter to PacifiCorp Energy regarding the plan to address the 2016 Dam Safety Inspection Follow-up letter for the Ashton Hydroelectric Project under P-2381. PDF
PDF
PDF
PDF
PPL MONTANA, L.L.C.
20161007-5105

P-2188
Letter to NorthWestern Energy accepting the STI Update for the Ryan Development of the Missouri-Madison Project under P-2188. PDF
PDF
PDF
PDF
PPL MONTANA, L.L.C.
20161007-5106

P-2188
Letter to NorthWestern Energy accepting the Plan and Schedule to update the STI and PFMA for the Black Eagle Development of the Missouri-Madison Project under P-2188. PDF
PDF
PDF
PDF
PPL MONTANA, L.L.C.
20161007-5108

P-2188
Letter to NorthWestern Energy regarding the 10th Part 12D Response including Plan and Schedule to address comments for the Morony Development of the Missouri-Madison Project under P-2188. PDF
PDF
PDF
PDF
PPL MONTANA, L.L.C.
20161007-5111

P-2188
Letter to NorthWestern Energy granting the Extension of Time to complete the Full-Height Spillway Gate Tests for the Morony, Holter and Hebgen Developments of the Missouri-Madison Project under P-2188. PDF
PDF
PDF
PDF
PPL MONTANA, L.L.C.
20161007-5082

P-5
Letter to Energy Keepers, Inc., regarding the Spillway Gate Repair Plan and Schedule for the Se?lis? Ksanka Ql?ispe? Project under P-5. PDF
PDF
PDF
PDF
PUBLIC UTILITY DISTRICT NO. 1 OF COWLITZ COUNTY, WASHINGTON
20161007-5065

P-2213
Letter to Cowlitz County PUD No. 1 acknowledging the Emergency Action Plan (EAP) 2016 Updates for the Swift No. 2 Project under P-2213. PDF
PDF
PDF
PDF
PUBLIC UTILITY DISTRICT NO. 1 OF DOUGLAS COUNTY, WASHINGTON
20161007-3017

P-2149
Letter to Public Utility No. 1 of Douglas County re the Revised Recreation Facilities and Amenities Tables for the Wells Hydroelectric Project under P-2149. PDF
PDF
PDF
PDF
PUBLIC UTILITY DISTRICT NO. 1 OF PEND OREILLE COUNTY, WASHINGTON
20161007-5063

P-2042
Letter to the Public Utility District No. 1 of Pend Oreille County Washington regarding the Dam Break Analysis and Inundation Maps for the Box Canyon Project under P-2042. PDF
PDF
PDF
PDF
PUERTO RICO ELECTRIC POWER AUTHORITY
20161007-3006

P-663
Notice of Intent to File License Application, Filing of Pre-Application Document, Approving Use of the Traditional Licensing Process re Puerto Rico Electric Power Authority under P-663. Word
PDF
Word
PDF
REEDSPORT OPT WAVE PARK, L.L.C.
20161007-3015

P-12713
Letter order accepting Reedsport OPT Wave Park, LLC.'s 7/1/16 filing of the Schedule for Removing Three Concrete Anchors re the Reedsport OPT Wave Park Project under P-12713. PDF
PDF
PDF
PDF
REYNOLDS IRRIGATION DISTRICT
20161007-5129

P-6229
Letter to Reynolds Irrigation District providing follow-up comments to the 2016 FERC Dam Safety Inspection of the Reynolds Irrigation District Project under P-6229. PDF
PDF
PDF
PDF
REYNOLDS IRRIGATION DISTRICT
20161007-5130

P-6229
Letter to Reynolds Irrigation District providing follow-up comments to the 2016 FERC Dam Safety Inspection of the Reynolds Irrigation District Project under P-6229. PDF
PDF
PDF
PDF
SE HAZELTON A L/P
20161007-5132

P-10164
Letter to Enel Green Power North America, Inc., regarding the Dam Break and Inundation Analysis for the Hazelton A Hydroelectric Project under P-10164. PDF
PDF
PDF
PDF
SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY
20161007-5073

P-3701
Letter to Burbank Water and Power regarding the EAP Contact List for the Tieton Project under P-3701. PDF
PDF
PDF
PDF
WARDS COVE PACKING COMPANY
20161007-5083

P-1432
Letter to PB Energy, Inc., accepting the plan and schedule for the 2015 Dam Safety Inspection Follow-up items for the Dry Spruce Bay Project under P-1432. PDF
PDF
PDF
PDF
FERC MISC
Case Title/
Accession Number
Docket NumberDescriptionFERC
EXELON CORPORATION
20161007-3012

AC16-203
Letter requesting Exelon Corporation to provide Accounting Docket Data Request within 20 days under AC16-203. Word
PDF
Word
PDF